K0521 · Hilltop Heights Health & Rehab Center (PA)
Surveyed 09/09/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Portable air conditioning units immediately taken down and removed on date of survey. No portable units remained in the facility and they were no longer needed due to facility's internal air…

View Full Plan Text
K0521 Correction Date: 09/21/2026 Portable air conditioning units immediately taken down and removed on date of survey. No portable units remained in the facility and they were no longer needed due to facility's internal air conditioning system functioning at that point. Maintenance director educated by nursing home administrator/designee that air conditioners cannot be vented into the corridor space above the ceiling.
K0521 · Graduate Post Acute (PA)
Surveyed 08/11/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. The portable air-conditioning unit that was improperly vented above the suspended ceiling in the basement laundry was removed from service. 2. The Maintenance Director/designee inspected…

View Full Plan Text
K0521 Correction Date: 09/23/2026 1. The portable air-conditioning unit that was improperly vented above the suspended ceiling in the basement laundry was removed from service. 2. The Maintenance Director/designee inspected the facility for other portable HVAC units that were improperly installed or vented. Identified concerns were corrected. 3. Maintenance staff were educated on properly installing and venting portable HVAC equipment according to manufacturer instructions and applicable Life Safety requirements. 4. The Maintenance Director/designee will audit the facility for improperly installed or vented portable HVAC equipment monthly for three months. Audit findings will be addressed and submitted to the Quality Assurance Performance Improvement Committee for further review and recommendation.
K0521 · Delaware Valley Veterans' Home (PA)
Surveyed 07/13/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

The approved regulatory guidelines for having dampers inspected every 4 years will be followed. The vendor, Berkshire Systems, Inc., was scheduled on 07/15/2026 to come out to the facility on…

View Full Plan Text
K0521 Correction Date: 09/11/2026 The approved regulatory guidelines for having dampers inspected every 4 years will be followed. The vendor, Berkshire Systems, Inc., was scheduled on 07/15/2026 to come out to the facility on Thursday, 07/23/2026, to replace the old damper and install a new damper and duct access door. This was completed and an access panel will also be added to the ceiling to make the damper accessible. Documentation of the noted actions will be obtained and maintained by the Facility Grounds Director in the Life Safety binder following completion of the installation. The Facility Grounds Director and Maintenance Supervisor completed refresher training on NFPA 80 and NFPA 90A damper requirements, with focus on maintaining accessible access panels. All future damper inspection reports will be reviewed within 72 hours of receipt, and any deficient practice will be assigned a due date, contractor confirmation and required documentation follow up. The Facility Grounds Director will review damper status quarterly until all repairs are complete, then semi-annually thereafter. Report from the Safety Committee chairs will be reviewed at the Quality Assurance Performance Improvement meeting and the Quality Assessment and Assurance (QAA)Committee will determine the need for additional audits/interventions for ongoing compliance.
K0521 · Cliveden Nursing and Rehabilitation Center (PA)
Surveyed 06/22/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

All HVACs will be properly vented to outside. Any HVAC that cannot be properly vented to outside will be removed. - Maintenance team conducted a tour of facility and there were no additional…

View Full Plan Text
K0521 Correction Date: 08/10/2026 - All HVACs will be properly vented to outside. Any HVAC that cannot be properly vented to outside will be removed. - Maintenance team conducted a tour of facility and there were no additional HVACs installed improperly. - administrator or designee will In-service the maintenance team on the importance of insuring all HVACs are properly ducted - Maintenance Director and/or team will conduct facility rounds weekly x 4 weeks to ensure compliance in all areas. - Results will be reported in monthly QAPI
K0521 · Yorkview Nursing and Rehabilitation (PA)
Surveyed 06/09/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Development and/or execution of this plan of correction does not constitute admission or agreement by this provider of the truth in the statement of deficiency. This plan of correction is…

View Full Plan Text
K0521 Correction Date: 07/24/2026 Development and/or execution of this plan of correction does not constitute admission or agreement by this provider of the truth in the statement of deficiency. This plan of correction is prepared and/or executed by provision of Federal or State Law. 1. The facility fire dampers have been inspected by 7/15/26. 2. The Maintenance Director updated the due date in the task list in the maintenance software to ensure that the fire dampers are inspected within 4 years. 3. The Maintenance Department will be educated by NHA that the scheduling of various facility inspections are to be completed per regulations. These inspections will be added to the task items in the maintenance software to ensure that they flag for completion according to established time frames. 4. NHA/Designee will review the life safety book annually to confirm the latest fire damper report is present and any deficiencies have been addressed. NHA/Designee will report on findings at the monthly Quality Assurance and Performance Improvement Committee to address further action planning or the need for further review. 5. Date of compliance: 7/24/26
K0521 · Walnut Creek Nursing and Rehab (PA)
Surveyed 05/20/2026 · Spot-checks: daily for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Facility Maintenance Director has been in contact with vendors to have fire/smoke damper access panel options quoted. Facility Maintenance Director completes daily fire alarm system panel…

View Full Plan Text
K0521 Correction Date: 07/16/2026 Facility Maintenance Director has been in contact with vendors to have fire/smoke damper access panel options quoted. Facility Maintenance Director completes daily fire alarm system panel checks to ensure system functionality. Facility Maintenance Director will ensure fire/smoke damper accesses are quoted, and a purchase order has been completed, down payment processed for work to be started with a timeline available for completion. Maintenance Director will conduct weekly Audits of the fire alarm panel for trouble signals for twelve weeks to ensure compliance. The results of these audits will be reviewed by the facility quality assurance and process improvement committee until substantial compliance is achieved.
K0521 · The Ball Pavilion (PA)
Surveyed 03/31/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

The three fire/smoke dampers noted as deficient on the facility's 3/31 inspection were repaired and brought into compliance as of April 6, 2026. Repairs were completed by Swartz, and…

View Full Plan Text
K0521 Correction Date: 04/09/2026 The three fire/smoke dampers noted as deficient on the facility's 3/31 inspection were repaired and brought into compliance as of April 6, 2026. Repairs were completed by Swartz, and documentation verifying completion was obtained by the Maintenance Director and submitted to the Administrator. The facility will continue routine maintenance and inspection of HVAC systems and fire/smoke dampers in accordance with NFPA 101 and facility preventive maintenance schedules to ensure ongoing compliance.
K0521 · York North Skilled Nursing and Rehabilitation Center (PA)
Surveyed 03/12/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. Unable to retroactively provide the 4-year fire damper maintenance and exercise completion report.The 4-year fire damper inspection and maintenance is scheduled to be performed on April 7,…

View Full Plan Text
K0521 Correction Date: 03/31/2026 1. Unable to retroactively provide the 4-year fire damper maintenance and exercise completion report.The 4-year fire damper inspection and maintenance is scheduled to be performed on April 7, 2026. 2. Audit of required 4-year fire damper maintenance and exercise completion report completed to determine if any additional reports were missing. 3. Education to be completed with Maintenance Director and Maintenance Assistant related to ensuring the 4-year fire damper maintenance and exercise completion report is completed timely. 4. Maintenance Director/Designee will conduct semi-annual audits x 3 quarters to ensure facility s4-year fire damper maintenance and exercise is performed timely.Results will be forwarded to the QAPI committee to determine the need for future follow up/monitoring.
K0521 · Onyx Nursing & Rehabilitation (PA)
Surveyed 03/11/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. Maintenance staff removed portable air conditioner from Nursing station 2. NHA/designee conducted audit to ensure no other portable air conditioners are venting into ceiling incorrectly. No…

View Full Plan Text
K0521 Correction Date: 04/08/2026 Preparation and submission of this Plan of Correction does not constitute an admission or agreement with the facts alleged or conclusions stated in the Statement of Deficiencies. This Plan of Correction is submitted solely because it is required by Federal and State regulations. 1. Maintenance staff removed portable air conditioner from Nursing station 2. NHA/designee conducted audit to ensure no other portable air conditioners are venting into ceiling incorrectly. No other issues identified. 3. NHA/ Designee educated maintenance staff on requirements to maintain HVAC system and ensure proper venting of portable Acs 4. NHA/designee Will audit facility weekly x 4 then monthly x2, to ensure all portable ACs are vented properly. results will be brought to QAPI for further evaluations and recommendations
K0521 · Kadima Rehabilitation & Nursing at Washington (PA)
Surveyed 01/20/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Based on documentation review and interview, it has been determined that the facility failed to ensure fire and smoke dampers were visually inspected and tested every four years.…

View Full Plan Text
K0521 Correction Date: 02/12/2026 -Based on documentation review and interview, it has been determined that the facility failed to ensure fire and smoke dampers were visually inspected and tested every four years. -Communication has been made with Mongiovi & Sons Fire Services about properly inspecting the fire dampers and it will be scheduled as soon as they can do it. - The Maintenance Director will be re-educated by the Licensed Administrator on the requirements and facility policy to ensure this testing is completed. -The Maintenance Director or designee will review quarterly to ensure completion of the plan of correction and report findings to the QA to ensure regulatory compliance.
K0521 · Fairview Rehab and Care Center (PA)
Surveyed 01/13/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

4-year smoke damper inspection obtained and was done on 3.31.2025 and passed inspection. Maintenance educated on the four year need and requirement by Regional Maintenance Director.…

View Full Plan Text
K0521 Correction Date: 03/03/2026 K0521 4-year smoke damper inspection obtained and was done on 3.31.2025 and passed inspection. Maintenance educated on the four year need and requirement by Regional Maintenance Director. Maintenance to present update at QAPI
K0521 · Graduate Post Acute (PA)
Surveyed 11/24/2025 · Spot-checks: monthly for 3 weeks
✓ Passed Re-Inspection Use K0521 →

Maintenance will have fire/smoke damper installed in oxygen room, vendor to come out on 12/14 to asses. A TLW may be requested. Maintenance will remove portable AC units in the kitchen,…

View Full Plan Text
K0521 Correction Date: 01/15/2026 Maintenance will have fire/smoke damper installed in oxygen room, vendor to come out on 12/14 to asses. A TLW may be requested. Maintenance will remove portable AC units in the kitchen, resident room, and 2nd floor nursing station Maintenance director will ensure portable AC units are not in the center. NHA/Designee will in-service maintenance director on usage of AC portable units NHA/Designee will audit center to ensure portable AC units are not being utilized. Audits will be completed three times a week for 3 weeks and 2 times monthly for 2 months. Audits will be reviewed by the QAPI committee during Quality Assurance meetings, and any variances will be addressed.
K0521 · Independence Rehab and Nursing (PA)
Surveyed 11/24/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. The Maintenance Director has contacted a vendor to conduct a Smoke/Fire Damper inspection. Documentation will be available upon completion of the inspection. 2. On 9/22/2025 the Maintenance…

View Full Plan Text
K0521 Correction Date: 12/29/2025 1. The Maintenance Director has contacted a vendor to conduct a Smoke/Fire Damper inspection. Documentation will be available upon completion of the inspection. 2. On 9/22/2025 the Maintenance Director reviewed documentation to verify that all other inspections for the HVAC system were current. 3. On 10/2/2025the NHA educated the maintenance team on maintaining and inspecting the HVAC system. 4. The Maintenance Director and/or designee will conduct audits weekly for 4 weeks of HVAC systems inspections and documentation are current. Results of the audits will be reviewed at the QAPI meeting held monthly.
K0521 · Monroeville Post Acute (PA)
Surveyed 11/19/2025 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. Paperwork was located. 2. Maintenance Director educated on K0521 and the need for immediate testing and inspection of the facility smoke dampers. 3. Maintenance to conduct monthly audit of…

View Full Plan Text
K0521 Correction Date: 12/03/2025 1. Paperwork was located. 2. Maintenance Director educated on K0521 and the need for immediate testing and inspection of the facility smoke dampers. 3. Maintenance to conduct monthly audit of preventative maintenance to fire safety system and report to safety committee and QAPI.
K0521 · Harborview Rehabilitation and Care Center at Doylestown (PA)
Surveyed 10/20/2025 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1- Facility contacted the HVAC vendor to schedule repair and testing of 31 failed fire dampers. 2. Maintenance staff will be re-educated on the 6-year inspection requirement for dampers and…

View Full Plan Text
K0521 Correction Date: 11/26/2025 1- Facility contacted the HVAC vendor to schedule repair and testing of 31 failed fire dampers. 2. Maintenance staff will be re-educated on the 6-year inspection requirement for dampers and maintaining documentation. 3. Maintenance Director/Designee will conduct audits of damper inspection records monthly x 2. 4. Results will be reported to the QAPI Committee.
K0521 · Aventura at Pembrooke (PA)
Surveyed 08/05/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

The facility failed to maintain air conditioning systems, on one of four floors. No residents were affected. All residents have the potential to be affected. The portable air conditioning…

View Full Plan Text
K0521 Correction Date: 09/12/2025 The facility failed to maintain air conditioning systems, on one of four floors. No residents were affected. All residents have the potential to be affected. The portable air conditioning unit, located in large common area near the Nurses' Station, was removed so it is not vented directly into the interstitial space of the ceiling. The expected date for HVAC to be repaired is September 30th 2025 with the portable air conditioners removed before 10/31/2025. An audit was completed by the Maintenance Director to ensure that no portable air conditioning units were vented directory into the interstitial space of the ceiling with no concerns and found to be in compliance. Director of Maintenance and maintenance staff were educated by the Administrator on the requirement. The Maintenance Director/Designee will conduct one weekly audit of the portable air conditioner for four weeks, then monthly for two months. Results of audits will be reviewed at the Quarterly Quality Assurance and Improvement Committee Meeting over the duration of the audit process. Based on the results of the audits, a decision will be made regarding the need for continued submission and reporting.
K0521 · Sanatoga Center (PA)
Surveyed 07/30/2025 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Vendor scheduled for damper repair The Maintenance Director will be reeducated by the NHA/Designee on K0521 with focus on the importance of ensuring fire damper inspections are being completed…

View Full Plan Text
K0521 Correction Date: 09/18/2025 Vendor scheduled for damper repair The Maintenance Director will be reeducated by the NHA/Designee on K0521 with focus on the importance of ensuring fire damper inspections are being completed and checking to ensure building is in compliance. Monthly audits to be completed x 4 to ensure valid fire damper inspection in place. Maintenance director/Designee will report findings of inspection at QAPI meeting
K0521 · King of Prussia Skilled Nursing and Rehabilitation Center (PA)
Surveyed 07/28/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

***Update**** Update***The HVAV in the Therapy is scheduled to be repaired and the portable HVAC Air Conditioning unit will be returned back to the Leasing Company. 1. The Maintenance Director…

View Full Plan Text
K0521 Correction Date: 08/28/2025 ***Update**** Update***The HVAV in the Therapy is scheduled to be repaired and the portable HVAC Air Conditioning unit will be returned back to the Leasing Company. 1.The Maintenance Director will contact the HVAC Vendor to come out to do the Repair 2.The NHA or designee will educate the Maintenance Director to ensure he complies with the Life Safety Code. 3.Facility audits will be completed to ensure the air conditioner units are in good working condition and comply with manufactures 9.2 installation specifications. 4.The Maintenance Director or designee will conduct the Audits Weekly x 4 and Monthly x 2 until compliance is reached. 5The findings of the audits will be shared with the QAPI Committee:Date of compliance: 8/28/25.
K0521 · Woodhaven Health & Rehab Center (PA)
Surveyed 07/08/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Director of Maintenance reached out to get a quote for the fire damper inspection. Director of Maintenance received a quote for the fire damper inspection. Director of Maintenance to schedule…

View Full Plan Text
K0521 Correction Date: 08/05/2025 Director of Maintenance reached out to get a quote for the fire damper inspection. Director of Maintenance received a quote for the fire damper inspection. Director of Maintenance to schedule fire damper inspection. The Director of Maintenance and maintenance staff were educated on the policy for damper inspections by the NHA. To monitor and maintain ongoing compliance the Director of Maintenance or designee will audit 5 facility fire dampers to ensure inspection is completed weekly x4 and monthly x1. Results will be taken to the QAPI for review and revision as needed.
K0521 · Ivy Park Post Acute (PA)
Surveyed 06/18/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

The inspection of the fire and smoke dampers of the entire facility was completed on 6/24/25. The Maintenance Director and Maintenance staff was educated by the NHA/Designee on the…

View Full Plan Text
K0521 Correction Date: 07/16/2025 The inspection of the fire and smoke dampers of the entire facility was completed on 6/24/25. The Maintenance Director and Maintenance staff was educated by the NHA/Designee on the requirements of NFPA 101 HVAC related to fire and smoke dampers inspections. The Maintenance Director will conduct an audit of all fire and smoke dampers to ensure inspection stickers are placed and are dated to meet the requirements. Audit will be presented at the facility QAPI committee meeting for review.
K0521 · Caring Heart Rehabilitation and Nursing Center (PA)
Surveyed 06/17/2025 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

Affected ceiling diffusers and vents were cleaned ,obstructions (e.g., paper towels) were removed. maintenance staff will be re-educated on proper vent cleaning and reporting procedures. The…

View Full Plan Text
K0521 Correction Date: 08/01/2025 Affected ceiling diffusers and vents were cleaned ,obstructions (e.g., paper towels) were removed. maintenance staff will be re-educated on proper vent cleaning and reporting procedures. The Director of Maintenance or designee will audit for compliance. Monthly audits times 3 will continue thereafter with results reported to the QA Committee by the Director of Maintenance or designee for the next three months
K0521 · Luther Crest Nursing Facility (PA)
Surveyed 06/16/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. Fire Damper preventative maintenance and a report to reference NFPA 90A were completed by Brand Services on 09/11/2024. This paperwork was located by the Maintenance Director. The paperwork…

View Full Plan Text
K0521 Correction Date: 07/03/2025 1. Fire Damper preventative maintenance and a report to reference NFPA 90A were completed by Brand Services on 09/11/2024. This paperwork was located by the Maintenance Director. The paperwork was not available at the time of the life safety inspection on 06/16/2025.
K0521 · Wecare at Monroeville Rehabilitation and Nursing Center (PA)
Surveyed 06/16/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

The facility will have our contracted fire prevention specialist inspect and test facility dampers. The Maintenance staff will be in-serviced on the requirements of K-0521 with a focus on…

View Full Plan Text
K0521 Correction Date: 08/12/2025 The facility will have our contracted fire prevention specialist inspect and test facility dampers. The Maintenance staff will be in-serviced on the requirements of K-0521 with a focus on damper inspection and testing requirements. The required damper inspection and testing service has been added to the new facility preventative maintenance monitoring program. Any concerns will be presented to the facility Quality Assurance Performance Improvement Committee.
K0521 · The Gardens at Easton (PA)
Surveyed 05/29/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. Maintenance department cleaned and exercised all fire dampers in the facility and it has been logged. 2. Maintenance department educated that fire dampers are to be cleaned and exercised…

View Full Plan Text
K0521 Correction Date: 07/28/2025 1. Maintenance department cleaned and exercised all fire dampers in the facility and it has been logged. 2. Maintenance department educated that fire dampers are to be cleaned and exercised every 4 years. 3. Maintenance Director/designee will perform a quarterly review on routine maintenance to ensure due dates are met. 4. Will report and abnormal findings to QAPI.
K0521 · Pottstown Skilled Nursing and Rehabilitation Center (PA)
Surveyed 05/01/2025 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0521 →

1. The facility cannot retroactively correct the missing documentation to indicate the completion of the four-year damper exercising/inspection. 2. The facility had the damper…

View Full Plan Text
K0521 Correction Date: 06/10/2025 1. The facility cannot retroactively correct the missing documentation to indicate the completion of the four-year damper exercising/inspection. 2. The facility had the damper exercised/inspected on March 25, 2025. The documentation of completion will be stored in the facility Life Safety binder. 3. The Director of Maintenance has been educated on the requirements of having the facility's fire dampers exercised and inspected within 4 years and storing the resulting inspection report in the facility Life Safety binder. 4. The facility's Life Safety binder will be audited quarterly to ensure placement and availability of the report for the 4 year facility fire damper exercising/inspection. Audit results will be reviewed at QAPI. 5. Date of compliance is June 10, 2025.