Past Winning Plans
Real state-approved Plans of Correction and their spot-check schedules.
Federal CMS Precedents Shown for Texas: CMS SOM § 7304 Plan-of-Correction rules apply nationwide. Below are verified Passed-Revisit examples you can adapt for Texas, or view local county stats in
Texas State Guides →
F0842 · Homewood Health Campus (IN)
Surveyed 06/16/2026 · Spot-checks: weekly for 4 weeks
1. Immediate actions taken for Physician. 2. How the facility identified other residents: All residents have the potential to be affected. 3. Measures put into place / System changes: All…
View Full Plan Text
F0842
Completion Date: 07/10/2026
1. Immediate actions taken for Physician.
2. How the facility identified other residents: All residents have the potential to be affected.
3. Measures put into place / System changes: All clinical staff were in-serviced on Medication Administration general guidelines SOP. DHS/designee will complete audits on Medication Administration general guidelines. DHS/designee to observe/audit medication passes to ensure compliance and accuracy on 5 residents weekly x six weeks, 5 residents bi-weekly x six weeks, 5 residents monthly x 3 months, or until 100% compliance is maintained.
4. How the corrective actions will be monitored: As a Quality measure, the results of the audit observations will be reported, reviewed, and trended for compliance though the facility Quality Assurance Committee for a minimum of 6 months to ensure substantial The submission of this plan of correction does not indicate an admission by Homewood Health Campus that the findings and allegations contained herein are accurate, true representation of the quality of care provided, and living environment provided to the residents of Homewood Health Campus. The facility recognizes its obligation to provide legally and medically necessary care and services to its residents in an economic and efficient manner. The facility hereby maintains it is in substantial compliance with all state and federal requirements compliance. R0214 Service Plan Evaluation
1. Immediate actions taken for those residents identified: Resident 25 was affected with no-adverse effects. Semiannual service plans were immediately completed.
2. How the facility identified other residents: All residents have the potential to be affected. Licensed clinical staff educated on AL Service Plan guidelines.
3. Measures put into place / System changes: As a measure of ongoing compliance, In house audit was completed for all AL residents. DHS or designee to review service plans for timely completion on 3 residents weekly x 3 months then monthly x 3 months or until 100% compliance is maintained.
4. How the corrective actions will be monitored: months to ensure substantial compliance is maintained of 100% compliance is met.
F0842 · The Waters of Castleton Skilled Nursing Facility (IN)
Surveyed 06/03/2026 · Spot-checks: weekly for 4 weeks
It is the intent of this facility to have complete and accurate documentation for residents to follow up physician documentation. What corrective action will be accomplished for those…
View Full Plan Text
F0842
Completion Date: 06/19/2026
It is the intent of this facility to have complete and accurate documentation for residents to follow up physician documentation. What corrective action will be accomplished for those residents found to have been affected by the deficient practice. Resident B no longer resides in the facility. How other residents having the potential to be affected by the same deficient practice will be therefore, this plan of correction plans to all residents that reside in the facility. What measures will be put in place and what systemic changes will be made to ensure that the deficient practice does not recur. The DON/Designee in-serviced nursing staff on scheduling follow-up appointments on 6/2/2026. Additionally, any staff member that fails to comply with the points of this in-service will be further educated and/or disciplined as indicated. How the corrective action will be monitored to ensure the deficient practice will not recur, i.e. what quality assurance program will be put into place. The DON/Designee will audit new orders, new admissions and re-admissions for follow up appointments and verify appointment scheduled five times a week x 4 weeks, then 3 times a week x 4 weeks, then once a week x 4 months. If the facility is within 95% compliance at the end of the 6 months; then monitoring can be Action Plan needed will be written by the QAPI committee. Any written Action Plan will be monitored by the Administrator weekly until resolved.
F0842 · Windsor Rehabilitation and Healthcare Center (NC)
Surveyed 01/13/2026 · Spot-checks: weekly for 3 months
1. Immediate corrective action: MAR/TAR review for all residents identified in the tag; MAR/TARs corrected per policy. Completed by the Director of Nursing on 1/7/2026. No further issues…
View Full Plan Text
F0842
Completion Date: 02/04/2026
1. Immediate corrective action: MAR/TAR review for all residents identified in the tag; MAR/TARs corrected per policy. Completed by the Director of Nursing on 1/7/2026. No further issues identified
2. Systemic changes: All residents have the potential to be effected by this deficient practice. 100% Medication Admin Audit report was ran on 1/30/26 and corrected. The Admin Audit report shows all the holes on the MAR/TARS, and the Nurses/CMA will be called to verify if the medication/treatment was completed and have them come back within appropriated timeframe to ensure that all medications/treatments were completed. The medication admin audit report will be ran 5 days a week by Director of Nursing or Designee, and all follow up will be followed up within 24 hours.
3. Measures to prevent recurrences: Education to all licensed nursing staff regarding MAR/TAR reconciliation at end of each shift will be completed before or by 2.2.26. Required education on documentation accuracy with Continued from page 29 Nursing with all licensed nursing/agency before or by 2/2/26, and ongoing due agency and new hires.
4. Monitoring: DON/designee will audit 5 MARs/TARs weekly x 12 weeks. Will review in QAPI for 3 months by the administrator.