K0918 · Margaret E. Moul Home (PA)
Surveyed 08/24/2026 · Spot-checks: monthly for 3 months
✓ Passed Re-Inspection Use K0918 →

1. Maintenance and testing of the generator and transfer switches will be performed in accordance with NFPA 110. One year monthly conductance testing and 30 minute load testing with transfer…

View Full Plan Text
K0918 Correction Date: 09/30/2026 1. Maintenance and testing of the generator and transfer switches will be performed in accordance with NFPA 110. One year monthly conductance testing and 30 minute load testing with transfer switch was completed and will continue to be completed each month by Director of Environmental Services or designee. Facility has also added an additional line on its monthly generator testing documentation form, to now include the actual number of minutes that the emergency generator runs for during required testing. 2. The emergency generator documentation form will be maintained according to the NFPA 101 standards. 3. Director of Environmental Services or designee will audit the emergency generator documentation monthly for 3 months, and then quarterly for 3 quarters. Findings will be reported to the Quality Assessment and Assurance Committee for recommendations and need for further audits.
K0918 · Graduate Post Acute (PA)
Surveyed 08/11/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. An appropriate battery conductance tester was obtained. The generator's maintenance-free batteries were tested, and the required conductance results were recorded in the generator…

View Full Plan Text
K0918 Correction Date: 09/23/2026 1. An appropriate battery conductance tester was obtained. The generator's maintenance-free batteries were tested, and the required conductance results were recorded in the generator maintenance records. 2. The Maintenance Director/designee reviewed the generator maintenance records. Missing battery tests and maintenance documentation were identified and corrected. 3. Maintenance staff were educated on generator battery conductance testing, required frequency, proper documentation, and record-retention requirements. 4. The Administrator/designee will audit generator maintenance records monthly for three months. Audit findings will be addressed and submitted to the Quality Assurance Performance Improvement Committee for further review and recommendation.
K0918 · Manchester Commons of Presbyterian Seniorcare (PA)
Surveyed 07/22/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. The new equipment for the maintenance free battery testing was received .The four hour load tests have been scheduled with Cleveland Brothers and will be completed by 8/6/2026, as will the…

View Full Plan Text
K0918 Correction Date: 09/14/2026 1. The new equipment for the maintenance free battery testing was received .The four hour load tests have been scheduled with Cleveland Brothers and will be completed by 8/6/2026, as will the battery conductance tests. The four hour load test has been entered into Worxhub so that the work orders will generate at the required cadence to assure this is not missed in the future. The battery conductance testing has been added to the Cummings monthly report and will be completed and reported to NHA monthly. 2. The survey results will be reviewed at our weekly and quarterly quality meeting, as will dates when corrective action will be completed.
K0918 · St. Anne Home (PA)
Surveyed 07/20/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. The generator inspection vendor under contract with St. Anne Home did not respond timely to the facility after repeated calls to schedule an inspection for the cited areas. A contract with…

View Full Plan Text
K0918 Correction Date: 08/07/2026 1. The generator inspection vendor under contract with St. Anne Home did not respond timely to the facility after repeated calls to schedule an inspection for the cited areas. A contract with a new vendor was established by the Director of Plant Operations to inspect the Annual Preventative Maintenance Test, Annual Load Bank Test, and the Annual Fuel Quality Test. 2. The inspection for the Annual Preventative Maintenance Test, Annual Load Bank Test, and Annual Fuel Quality Test was scheduled for August 5 and 6 by the Director of Plant Operations. 3. The Nursing Home Administrator educated the Director of Plant Operations to obtain a back-up contract with another generator inspection vendor to prevent this situation from recurring. 4. The schedule for these facility annual tests with due dates for the tests will be reviewed by the Director of Plant Operations at the monthly QAPI meeting on 7/31/26, to add generator audits as a standing agenda item in the QAPI meetings.
K0918 · Aventura at Pembrooke (PA)
Surveyed 07/08/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

0918: Electrical Systems - Essential Electric System: The facility failed to provide documentation verifying a four-hour exercise, under load, of the emergency generator had occurred, within…

View Full Plan Text
K0918 Correction Date: 08/05/2026 0918: Electrical Systems - Essential Electric System: The facility failed to provide documentation verifying a four-hour exercise, under load, of the emergency generator had occurred, within the previous 36 months, and to provide documentation verifying the quality of the diesel fuel servicing the emergency generator had been tested. No residents were affected. All residents have the potential to be affected. A four-hour exercise, under load, of the emergency generator was performed per regulation and documented by the Maintenance Director on 15JUL2026. Diesel fuel servicing the generator was tested and documented per regulatory requirements on 15JUL2026 by the Maintenance Director. On 21JUL2026, NHA educated the Maintenance Director on the importance of performing required generator testing every 36 months and diesel fuel testing monthly, while maintaining documentation per regulatory requirements. The Maintenance Director/Designee will conduct compliance audits monthly, to ensure that documentation for generator testing and diesel fuel testing meet the regulatory requirement. NHA/Designee will audit annually Life Safety Binder with Maintenance Director to ensure compliance. Results will be submitted to the quarterly Quality Assurance Performance Improvement Committee for review and recommendations.
K0918 · Germantown Home (PA)
Surveyed 07/01/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

During Life Safety Survey it was identified that one out of nine generator reports the Annual 90-minute load bank test documentation could not be identified as being completed. The maintenance…

View Full Plan Text
K0918 Correction Date: 08/25/2026 During Life Safety Survey it was identified that one out of nine generator reports the Annual 90-minute load bank test documentation could not be identified as being completed. The maintenance director has scheduled the 90-minute load bank test to be completed. Education with maintenance team on importance of generator testing and scheduling to be completed. Maintenance Director will place the annual 90-minute load bank test for the generator in the TEL's maintenance calendar as a reminder for maintenance team. Maintenance Director will report in QAPI confirmed 90-minute load bank test for 1 month. Corrective Action Date- 08/25/2026
K0918 · Scranton Health Care Center (PA)
Surveyed 06/24/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

Step 1: The facility has confirmed that Mechanical Services will be on site at the building on 7/15/2026 to do a Generator Fuel Test. Step 2: To identify like situations, facility will monitor…

View Full Plan Text
K0918 Correction Date: 07/21/2026 Step 1: The facility has confirmed that Mechanical Services will be on site at the building on 7/15/2026 to do a Generator Fuel Test. Step 2: To identify like situations, facility will monitor the maintenance documentation of the generator Step 3: To prevent this from happening again, the Maintenance Director will educate the company that services the generator on follow through of documentation and results that need attention. Step 4 To monitor and maintain ongoing compliance Maintenance Director will audit all documentation related to the generator monthly x 6 to ensure compliance. The results of the audits will be forwarded to the facility QAPI committee for further review and recommendations.
K0918 · Avalon Care Center (PA)
Surveyed 06/16/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

Maintenance Department will be reeducated on essential electric system maintenance and testing for emergency generators by the Nursing Home Administrator. Education will include monthly…

View Full Plan Text
K0918 Correction Date: 07/16/2026 Maintenance Department will be reeducated on essential electric system maintenance and testing for emergency generators by the Nursing Home Administrator. Education will include monthly 30-minute load testing, monthly battery testing, weekly battery voltage and visual inspection. Maintenance department will review all documentation monthly with the Nursing Home Administrator.
K0918 · Yorkview Nursing and Rehabilitation (PA)
Surveyed 06/09/2026 · Spot-checks: weekly for 2 months
✓ Passed Re-Inspection Use K0918 →

Development and/or execution of this plan of correction does not constitute admission or agreement by this provider of the truth in the statement of deficiency. This plan of correction is…

View Full Plan Text
K0918 Correction Date: 07/24/2026 Development and/or execution of this plan of correction does not constitute admission or agreement by this provider of the truth in the statement of deficiency. This plan of correction is prepared and/or executed by provision of Federal or State Law. 1. The weekly battery voltage inspection and the 3 year, 4hr generator load test was completed. 2. Completion date 6/18/26. 3. The Maintenance Director has been educated on conducting and documenting weekly visual inspections of the battery voltage on the emergency generator log and scheduling in advance the 3 year, 4hr generator load test. 4. Maintenance Director/designee will audit weekly the battery voltage and report for 2 months the completions of the weekly visual inspections of the battery voltage and the scheduling plan for the 3 year, 4hr generator load test at the monthly Quality Assurance and Performance Improvement Committee to address any trends or patterns for further review and/or recommendations. 5. Date of compliance: 7/24/26
K0918 · Holy Family Manor (PA)
Surveyed 06/08/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. The emergency fuel reserve was verified and sampled by Albarell Electric Inc. on June 11th, 2026. The remote generator annunciator was assessed by Albarell Electric Inc. and is working…

View Full Plan Text
K0918 Correction Date: 07/31/2026 1. The emergency fuel reserve was verified and sampled by Albarell Electric Inc. on June 11th, 2026. The remote generator annunciator was assessed by Albarell Electric Inc. and is working properly. Facility Maintenance will ensure this testing is completed annually. 2. Maintenance Director/Designee will conduct random generator and line power audits to ensure generator and line power are working properly. Findings will be reported during our QAPI meeting.
K0918 · Caring Heart Rehabilitation and Nursing Center (PA)
Surveyed 06/03/2026 · Spot-checks: daily for 4 weeks
✓ Passed Re-Inspection Use K0918 →

The emergency generator block heater, oil cooler, and valve covers were repaired/replaced, and the front desk annunciator panel trouble mode was cleared. - The Maintenance Director was…

View Full Plan Text
K0918 Correction Date: 07/20/2026 - The emergency generator block heater, oil cooler, and valve covers were repaired/replaced, and the front desk annunciator panel trouble mode was cleared. - The Maintenance Director was re-educated on tracking generator service report deficiencies and monitoring annunciator errors. - The Director of Maintenance or designee will inspect the annunciator panel daily and verify logs weekly. Monthly audits times 3 will continue with results reported to the QA Committee.
K0918 · Quality Life Services - New Castle (PA)
Surveyed 05/27/2026 · Spot-checks: monthly for 3 months
✓ Passed Re-Inspection Use K0918 →

Revision cannot be made to prior documentation. Maintenance Director Educated on Electrical Systems requirements. Audits will be completed monthly times 3 for 3 months. Results will be brought…

View Full Plan Text
K0918 Correction Date: 07/14/2026 Revision cannot be made to prior documentation. Maintenance Director Educated on Electrical Systems requirements. Audits will be completed monthly times 3 for 3 months. Results will be brought to QAPI
K0918 · Luther Crest Nursing Facility (PA)
Surveyed 05/19/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. Curtis Power Solutions, the contractor performing facility generator p.m.'s, has been notified to take a fuel quality sample during the next scheduled maintenance/filter change that is…

View Full Plan Text
K0918 Correction Date: 06/05/2026 1. Curtis Power Solutions, the contractor performing facility generator p.m.'s, has been notified to take a fuel quality sample during the next scheduled maintenance/filter change that is pending completion June 2026. 2. Maintenance Director/Designee will ensure that the diesel generator has a fuel quality sample done and recorded for the preceding twelve-month period.
K0918 · Chambersburg Skilled Nursing and Rehabilitation Center (PA)
Surveyed 05/18/2026 · Spot-checks: weekly for 2 months
✓ Passed Re-Inspection Use K0918 →

1. and2. Maintenance Director has completed weekly and monthly inspection/testing of facilities emergency generator since April 2026 to current. 3. Maintenance department will be educated on…

View Full Plan Text
K0918 Correction Date: 06/19/2026 1.and2. Maintenance Director has completed weekly and monthly inspection/testing of facilities emergency generator since April 2026 to current. 3. Maintenance department will be educated on the standards of ensuring the facility has completed the weekly/monthly inspection/testing of facilities emergency generator. 4. Maintenance or facility designee will audit the facilities weekly/monthly inspection/testing of the facilities emergency generator weekly for 2 months, then every 60 days throughout the year and results of the audit will be reported to the QAPI committee.
K0918 · Laurel Lakes Rehabilitation and Wellness Center (PA)
Surveyed 05/06/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. Repairs and adjustments will be completed as needed to ensure transfer of emergency power occurs within 10 seconds. 2. An annual verification process was implemented to confirm 10-second…

View Full Plan Text
K0918 Correction Date: 06/25/2026 1. Repairs and adjustments will be completed as needed to ensure transfer of emergency power occurs within 10 seconds. 2. An annual verification process was implemented to confirm 10-second transfer compliance when monthly testing is not met. 3. Staff involved in generator testing and maintenance were educated on NFPA requirements for: - 10-second emergency power transfer standard. - Proper documentation of transfer times Required actions when transfer times exceed limits. 4. Director of Plant Operations/designee will review monthly generator test results for compliance with the 10-second transfer requirement. Any variance will trigger corrective action and annual verification testing. Results will be tracked through the QAPI program.
K0918 · Rose City Nursing and Rehab at Lancaster (PA)
Surveyed 05/06/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

The 3 year 4 hour load bearing test of the emergency generator was conducted on 11-13-2023 and has been acquired and filed in the life safety book. Next one is due November 2026. Facility had…

View Full Plan Text
K0918 Correction Date: 06/30/2026 The 3 year 4 hour load bearing test of the emergency generator was conducted on 11-13-2023 and has been acquired and filed in the life safety book. Next one is due November 2026. Facility had 2 hour emergency generator load bearing tests completed on 10-10-2024 and 10-22-2025. 2. Maintenance Director contacted Power Systems Electric, Inc and they are scheduled to conduct 3 year 4 hour emergency generator load bearing test in November 2026. An audit will be conducted annually after testing in November 2026 to ensure it is filed in the life safety book. Results of audits will be submitted to monthly QAPI for review and recommendations.
K0918 · Twinbrook Healthcare and Rehabilitation Center (PA)
Surveyed 04/22/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. The facility had a 4-hour load test completed on 9/15/2025 The facility had a routine generator inspection on March 30, 2026 which identified the pin hole leak in the upper radiator pipe,…

View Full Plan Text
K0918 Correction Date: 05/08/2026 1. The facility had a 4-hour load test completed on 9/15/2025 The facility had a routine generator inspection on March 30, 2026 which identified the pin hole leak in the upper radiator pipe, the oil cooler leaking oil and the need for a replacement battery. The facility is waiting to receive the quote, once we receive it, we will work on having the repairs completed. 2. The Nursing Home Administrator will re-educate the maintenance department on the requirements for maintaining proper documentation for the quarterly generator testing. Any new maintenance personnel will receive training within one week of employment. 3. The facility will continue with the quarterly inspection of the generator. Any issues identified will be corrected in a timely manner. The Maintenance director or Designee will ensure that all components are fixed and tested with documentation. The results will be reported to the Quality Assurance and Performance Improvement Committee for review at the next monthly meeting.
K0918 · Pleasant Acres Rehabilitation and Nursing Center (PA)
Surveyed 04/21/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

This provided submits the following plan of correction in good faith and to comply with Federal regulations. This plan is not an admission of wrong doing nor does it reflect agreement with the…

View Full Plan Text
K0918 Correction Date: 06/04/2026 This provided submits the following plan of correction in good faith and to comply with Federal regulations. This plan is not an admission of wrong doing nor does it reflect agreement with the facts and conclusions stated in the statement of deficiencies. On 4/29/2026 the fuel company took a sample from fuel tank for a fuel quality test. The maintenance department will be in-serviced by NHA/designee on the importance having a retest done of the fuel supply after corrections were completed from recommendations from the initial test. A yearly audit will be performed by the Maintenance Director or designee to ensure fuel supply is tested and results actioned timely. Results of the audits will be reviewed/reported to QA committee to determine trends, compliance. QA committee will determine need for continuance of audits.
K0918 · The Ball Pavilion (PA)
Surveyed 03/31/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

The facility identified a lack of documentation for the required 36-month, 4-hour generator load test. Cleveland Brothers is scheduled to complete the required testing on 4/10/26, at which…

View Full Plan Text
K0918 Correction Date: 04/09/2026 The facility identified a lack of documentation for the required 36-month, 4-hour generator load test. Cleveland Brothers is scheduled to complete the required testing on 4/10/26, at which time the generator will be exercised for four continuous hours in accordance with NFPA requirements. Upon completion, documentation for the test will be maintained and made available for review. The Maintenance Director is responsible for ensuring completion of testing and will provide documentation to the Administrator. The facility will ensure this required testing is completed every three years moving forward.
K0918 · Abbeyville Skilled Nursing and Rehabilitation Center (PA)
Surveyed 03/17/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. Education provided to maintenance department on requirements of K918. Contact obtained for ongoing generator testing from vendor. Annual load bank test to be completed 4/30/26. 2. Audits…

View Full Plan Text
K0918 Correction Date: 05/13/2026 1. Education provided to maintenance department on requirements of K918. Contact obtained for ongoing generator testing from vendor. Annual load bank test to be completed 4/30/26. 2. Audits will be completed monthly x 4 months to ensure maintenance and testing done in accordance with regulations and then semi-annually thereafter ( to include receipt of documentation from vendor, filing in life safety book and next test being scheduled). 3. Audits will be brought to QAPI committee until substantial compliance is demonstrated. 4. Date of Compliance: 5/13/2026
K0918 · Carnegie Park Post Acute (PA)
Surveyed 03/10/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

The facility has corrected the deficiency. Called contracted company for generator and all required emergency generator inspections, testing, and maintenance were completed, including weekly…

View Full Plan Text
K0918 Correction Date: 04/27/2026 The facility has corrected the deficiency. Called contracted company for generator and all required emergency generator inspections, testing, and maintenance were completed, including weekly inspections, monthly battery and transfer switch testing, annual preventive maintenance, fuel quality testing, and required load bank testing. Documentation has been established and maintained on-site for all required intervals. A tracking system has been implemented to ensure all future testing and maintenance are completed timely. The Maintenance Director or designee will monitor compliance by reviewing generator logs and service records on a routine basis.
K0918 · Manatawny Center for Rehabilitation and Nursing (PA)
Surveyed 03/04/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. The Maintenance Director scheduled and completed the annual 90-minute load bank test with the generator vendor on March 6, 2026. The test report has been placed in the Life Safety Book. All…

View Full Plan Text
K0918 Correction Date: 03/31/2026 1.The Maintenance Director scheduled and completed the annual 90-minute load bank test with the generator vendor on March 6, 2026. The test report has been placed in the Life Safety Book. All future required annual load bank tests will be scheduled and completed in accordance with NFPA 110 requirements. 2.The Maintenance Director and relevant staff members will be educated on NFPA 110 Electrical Systems - Essential Electric System requirements, with specific focus on the requirement for annual 90-minute load bank testing and documentation. 3.The Maintenance Director/designee will maintain written records of all generator maintenance and testing in the Life Safety Book, including weekly inspections, monthly load tests, and annual load bank tests. The NHA/designee will review the documentation during monthly audits to verify completion and availability. 4.Findings will be reviewed at the Quality Assurance Performance Improvement meeting
K0918 · Nightingale Nursing and Rehab Center (PA)
Surveyed 02/25/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

The generator's fuel sensor will be replaced. The results of the generator's annual fuel sample will be provided for the facility's records. No further action is required. To ensure ongoing…

View Full Plan Text
K0918 Correction Date: 03/23/2026 The generator's fuel sensor will be replaced. The results of the generator's annual fuel sample will be provided for the facility's records. No further action is required. To ensure ongoing compliance, a weekly audit to ensure that there are no faults on the generator's annunciator panels will be conducted. This audit will be the responsibility of the Maintenance Supervisor and/or designee. This audit will occur weekly x 4 weeks, then every other week for a month, then monthly until practice is determined to be in compliance. Corrective action will be taken immediately on identification. Audits will be reviewed no less than quarterly by Quality Assurance Performance Improvement committee.
K0918 · Norriton Square Nursing and Rehabilitation Center (PA)
Surveyed 01/30/2026 · Spot-checks: weekly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

The emergency generator is at the correct temperature and is functioning. The facility Maintenance Director was educated on the requirements for monitoring the emergency generator temperature.…

View Full Plan Text
K0918 Correction Date: 03/08/2026 The emergency generator is at the correct temperature and is functioning. The facility Maintenance Director was educated on the requirements for monitoring the emergency generator temperature. The Maintenance Director will complete a weekly audit x 12 weeks of the following emergency generator temperature checks. Emergency Generator temperature results will be reviewed monthly at the QAPI meeting x3 to ensure compliance.
K0918 · Greenfield Healthcare and Rehabilitation Center (PA)
Surveyed 01/28/2026 · Spot-checks: monthly for 4 weeks
✓ Passed Re-Inspection Use K0918 →

1. Documentation has been provided for the following tests on the emergency generator: a. Monthly battery conductance test (sealed battery) b. Annual 90 minute load bank c. Three year, 4 hour…

View Full Plan Text
K0918 Correction Date: 02/24/2026 1. Documentation has been provided for the following tests on the emergency generator: a. Monthly battery conductance test (sealed battery) b. Annual 90 minute load bank c. Three year, 4 hour load test. 2. Documentation will be maintained in a specific order in the documentation book for review of life safety individuals. 3. Quality Assurance will receive a monthly report of outside vendor tests conducted and monitored by the Maintenance Director.