K0342 · Germantown Home (PA)
Surveyed 07/01/2026 · Spot-checks: weekly for 4 weeks
The smoke detector was dislodged (hanging) from ceiling. The fire alarm reattached/corrected immediately. All staff will be educated to report immediately any smoke detectors seen…
View Full Plan Text
K0342 Correction Date: 08/25/2026
The smoke detector was dislodged (hanging) from ceiling. The fire alarm reattached/corrected immediately. All staff will be educated to report immediately any smoke detectors seen dislodged/hanging to the maintenance director, maintenance tech, or supervisor, for immediate repair. Three months of weekly audits of smoke detectors in 2nd floor break room will be done. The Maintenance Director will review monthly audit findings in QAPI for three months.
K0342 · Monticello House (PA)
Surveyed 06/24/2026 · Spot-checks: weekly for 4 weeks
The 5th floor elevator lobby smoke detector will be remounted to the ceiling. As a part of the Maintenance Supervisor's quarterly inspection protocol, they will inspect smoke detectors for…
View Full Plan Text
K0342 Correction Date: 07/20/2026
The 5th floor elevator lobby smoke detector will be remounted to the ceiling. As a part of the Maintenance Supervisor's quarterly inspection protocol, they will inspect smoke detectors for proper mounting. Any area identified will be addressed accordingly. Director of Facility Operations and/or delegate will report areas of concerns, findings, and corrections to the Quality Assurance Performance Improvement (QAPI) Committee for the next two quarters. Disclaimer: Preparation and/or execution of this entire Plan of Correction does not constitute admission or agreement by the Provider of the truth of the facts alleged or conclusion set forth in this Statement of Deficiencies. The entire Plan of Correction is prepared and/or executed solely because it is required by the provisions of Federal and State laws.
K0342 · Ivory Nursing & Rehabilitation (PA)
Surveyed 11/24/2025 · Spot-checks: weekly for 4 weeks
The cart was immediately removed from the areas obstructing the fire pull stations. A sign was placed on the wall in the affected areas that states "no equipment shall be placed in this area"…
View Full Plan Text
K0342 Correction Date: 12/30/2025
The cart was immediately removed from the areas obstructing the fire pull stations. A sign was placed on the wall in the affected areas that states "no equipment shall be placed in this area" All residents may be affected by this deficient practice. Nursing staff will be educated not to place equipment or carts in areas with a fire pull station. Maintenance director or designee will perform random facility audits weekly, x 4 weeks to ensure that areas with fire pull stations are not obstructed. Findings of these audits will be presented at the facility's QAPI meeting. It will be determined at that time if continued audits are necessary.
K0342 · Onyx Nursing & Rehabilitation (PA)
Surveyed 05/27/2025 · Spot-checks: weekly for 4 weeks
1. Maintenance Director Repaired smoke detector at lower level corridor near Maintenance Directors Office, ensuring it is securely mounted to ceiling 2. Maintenance Director / Designee…
View Full Plan Text
K0342 Correction Date: 07/01/2025
1. Maintenance Director Repaired smoke detector at lower level corridor near Maintenance Directors Office, ensuring it is securely mounted to ceiling
2. Maintenance Director / Designee completed audits of smoke detectors ensuring they are properly mounted and in satisfactory condition.
3. Maintenance Director educated on requirements to ensure smoke detectors are securely mounted and in good condition.
4. Maintenance Director / Designee will continue to audit smoke detectors weekly x 4 then monthly x 2.
K0342 · Immaculate Mary Center for Rehabilitation & Healthcare (PA)
Surveyed 04/28/2025 · Spot-checks: weekly for 4 weeks
This provider submits the following plan of correction in good faith and to comply with Federal Law. This plan is not an admission of wrongdoing, nor does it reflect agreement with the facts…
View Full Plan Text
K0342 Correction Date: 06/01/2025
This provider submits the following plan of correction in good faith and to comply with Federal Law. This plan is not an admission of wrongdoing, nor does it reflect agreement with the facts and conclusions stated in the statement of deficiencies. It is the practice of the facility to have proper installation of smoke detectors.
1. The smoke detector not securely installed to the ceiling box in basement has been installed correctly
2. All other smoke detectors have been checked and are properly installed.
3. Education is completed with Maintenance staff to confirm proper installation to fire alarm initiating devices.
4. Every quarter for a year the Maintenance Director or designee will check random smoke detectors to ensure they are properly mounted. This information will then be entered on a log and will be presented to the QAPI meeting.
K0342 · Inglis House (PA)
Surveyed 03/25/2025 · Spot-checks: weekly for 4 weeks
1) At the 2 Center Urological Supplies Closet, the out of service detector from a prior system will be removed. 2) To prevent this condition the Engineering Service Director will tour and…
View Full Plan Text
K0342 Correction Date: 05/06/2025
1) At the 2 Center Urological Supplies Closet, the out of service detector from a prior system will be removed. 2) To prevent this condition the Engineering Service Director will tour and check the entire facility including closets to identify any other areas this out of service component may still be. If any are any found they will be removed. 3) A work order for this task will be generated from the Engineering Services Maintenance Database and Work Order System Mp2, completed and kept on file for review when follow up survey occurs. The Director of Engineering services/ designee Will Monitor This Plan