Nebraska K-351 Plan of Correction Guide

K0351 · Smoke Deficiencies

Build K-351 Plan & Binder →
✓ 2025–26 NE Citations: 19
✓ Common Audit Schedule: weekly for 4 weeks
✓ Checklist Source: CMS Life Safety Code

In Nebraska, state surveyors recorded 19 citations for K0351 (K-351: Smoke Deficiencies) across recent 2025-2026 skilled nursing facility inspections. Recent citations in Nebraska were most active in Douglas, Lancaster, Hall counties. To clear an onsite revisit without repeat deficiencies, Maintenance Director or designee teams typically pair immediate resident or building remediation with signed staff shift huddles and weekly for 4 weeks audit logs reviewed by the monthly QAPI committee.

Active NE Counties: Douglas County (7) → Lancaster County (3) → Hall County (2) → Washington County (1) → Saunders County (1) →

What Surveyors Check Onsite

  • Are physical building zones cited under K0351 inspected on every shift and logged in the maintenance binder?
  • Have maintenance staff verified and documented immediate physical repair with dated work orders?
  • Are weekly audit logs signed by the Maintenance Director and reviewed at monthly QAPI meetings?

3-Question Hallway Spot-Quiz

Review with nurses & CNAs during your 5-minute shift huddle:

  1. If you spot an equipment or corridor safety issue related to K-351, how do you report an urgent maintenance order?
  2. Where are weekly Life Safety inspection logs kept when state surveyors arrive?
  3. What safety check happens on your unit before ending your shift?

Approved State Plan Examples for K0351

Margaret E. Moul Home (PA)
Spot-checks: weekly × 4 weeks ✓ Passed Re-Inspection

1. The 2 upright sprinkler heads located in the laundry room dryer change have been relocated down by Johnson Controls, to ensure a minimum of 1 inch from the overhead. 2. All upright…

View Full Plan Text (08/24/2026)
K0351 Correction Date: 09/30/2026 1. The 2 upright sprinkler heads located in the laundry room dryer change have been relocated down by Johnson Controls, to ensure a minimum of 1 inch from the overhead. 2. All upright sprinkler heads will be inspected to ensure they were installed with a minimum of 1 inch clearance from the overhead. 3. Director of Environmental Services or designee will audit upright sprinkler heads quarterly for 3 quarters to ensure compliance. Findings will be reported to the Quality Assessment and Assurance Committee for recommendations and need for further audits.
Richland Bean Blossom Health Care Center (IN)
Spot-checks: monthly × 4 weeks ✓ Passed Re-Inspection

Safe Care was immediately contacted to replace the eschutcheon in resident room to ensure it was seated flush with the ceiling leaving an inch annular space around the sprinkler head. A…

View Full Plan Text (04/27/2026)
K0351 Safe Care was immediately contacted to replace the eschutcheon in resident room to ensure it was seated flush with the ceiling leaving an inch annular space around the sprinkler head. A deficiency in this practice has the potential to affect staff and 16 residents. A facility audit was conducted to ensure that all sprinkler plates are seated flush with the ceiling leaving an inch of annular space Audits for the appropriate seating and placement of sprinkler plates will be completed by the Maintenance Director or designee monthly x 6 months or until 100% compliance is achieved. Results of these audits will be presented to the QA committee, and any recommendations for changes or updates by the QA committee will be put into place as indicated. These systemic changes will be in place on or before 05/30/2026
Customize & Print 4-Sheet Revisit Binder →