Nebraska K-300 Plan of Correction Guide

K0300 · Egress Deficiencies

Build K-300 Plan & Binder →
✓ 2025–26 NE Citations: 10
✓ Common Audit Schedule: weekly for 4 weeks
✓ Checklist Source: CMS Life Safety Code

In Nebraska, state surveyors recorded 10 citations for K0300 (K-300: Egress Deficiencies) across recent 2025-2026 skilled nursing facility inspections. Recent citations in Nebraska were most active in Saline, Richardson, Platte counties. To clear an onsite revisit without repeat deficiencies, Maintenance Director or designee teams typically pair immediate resident or building remediation with signed staff shift huddles and weekly for 4 weeks audit logs reviewed by the monthly QAPI committee.

Active NE Counties: Saline County (1) → Richardson County (1) → Platte County (1) → Otoe County (1) → Jefferson County (1) →

What Surveyors Check Onsite

  • Are physical building zones cited under K0300 inspected on every shift and logged in the maintenance binder?
  • Have maintenance staff verified and documented immediate physical repair with dated work orders?
  • Are weekly audit logs signed by the Maintenance Director and reviewed at monthly QAPI meetings?

3-Question Hallway Spot-Quiz

Review with nurses & CNAs during your 5-minute shift huddle:

  1. If you spot an equipment or corridor safety issue related to K-300, how do you report an urgent maintenance order?
  2. Where are weekly Life Safety inspection logs kept when state surveyors arrive?
  3. What safety check happens on your unit before ending your shift?

Approved State Plan Examples for K0300

Hickory Creek at Peru (IN)
Spot-checks: monthly × 30 days ✓ Passed Re-Inspection

The Maintenance Director immediately inspected and cleaned all battery smoke alarms. Documentation of the inspection and cleaning indicated in the facilities will be identified and what…

View Full Plan Text (01/15/2026)
K0300 Completion Date: 01/31/2026 It is the policy of this facility to ensure there is documentation for preventative maintenance of battery-operated smoke alarms in resident rooms. What corrective action(s) will be accomplished for those residents found to have been affected by the deficient practice: The Maintenance Director immediately inspected and cleaned all battery smoke alarms. Documentation of the inspection and cleaning indicated in the facilities will be identified and what corrective action(s) will be taken. All residents have the potential to be affected by this finding. The battery-operated smoke alarms were checked and cleaned. Documentation of the inspection and cleaning indicated in the facilities Preventative Maintenance Program. What measures will be put into place or what systemic changes will be made to ensure that the deficient practice does not recur: The Maintenance Director will inspect the functionality of all battery smoke alarms during the facilities Preventative Maintenance rounds to ensure they are clean and functioning. Documentation of the inspection and cleaning indicated in the facilities Preventative Maintenance Program. How the corrective action(s) will be monitored to ensure the deficient practice will not recur, i.e., what quality assurance program will be put into place. Audits on the battery-operated smoke alarms will be completed monthly. If the threshold is not 100% met, an action plan will be submitted to the Safety Committee for review and follow-up. be accomplished for those residents found to have been affected by the alleged deficient practice. resident room door - Self closing hinges installed to ensure automatic closure. How will you identify other residents having the potential to be affected by the same alleged deficient practice and what corrective action will be taken. All residents have the potential to be affected by the alleged deficient practice. A tour was conducted with the surveyor of the remainder of the building, and all doors were compliant and had properly installed hinges. What measures will be put into place or what systemic changes you will make to ensure that the alleged deficient practice does not recur. Maintenance will conduct door checks to ensure all self closing doors are properly working. If any doors are found to be at fault, a work order will be created and repairs will be quality assurance program will be put into place. Maintenance will conduct door checks these checks will be conducted 2 times a week for 30 days, then monthly thereafter if during the first 30 days no doors were found to be faulty. If a door(s) are identified as faulty, maintenance will repair the door(s) and develop an action plan to be submitted to the Safety Committee for review and follow up.
Brickyard Healthcare - Twelfth Street Care Center (IN)
Spot-checks: weekly × 4 weeks ✓ Passed Re-Inspection

Battery operated smoke detectors are now being tested weekly and cleaned monthly and records are being properly kept. Detectors within 36 inches of the air ducts in resident rooms were moved…

View Full Plan Text (12/09/2025)
K0300 Completion Date: 02/03/2026 Battery operated smoke detectors are now being tested weekly and cleaned monthly and records are being properly kept. Detectors within 36 inches of the air ducts in resident rooms were moved away to greater than 36 inches from the air duct. A task was added to TELS to Test all battery operated A monthly task was added to TELS for Battery Operated Smoke Detector Cleaning. Maintenance will report to QAPI no less than quarterly in perpetuity regarding life safety issues.
Customize & Print 4-Sheet Revisit Binder →