2025–26 MI Citations: 39
✓
Common Audit Schedule: weekly for 4 weeks
✓
Checklist Source: CMS Life Safety Code
In Michigan, state surveyors recorded 39 citations for K0761 (K-761: Miscellaneous Deficiencies) across recent 2025-2026 skilled nursing facility inspections. Recent citations in Michigan were most active in Wayne, Oakland, Macomb counties. To clear an onsite revisit without repeat deficiencies, Maintenance Director or designee teams typically pair immediate resident or building remediation with signed staff shift huddles and weekly for 4 weeks audit logs reviewed by the monthly QAPI committee.
What Surveyors Check Onsite
- Are physical building zones cited under K0761 inspected on every shift and logged in the maintenance binder?
- Have maintenance staff verified and documented immediate physical repair with dated work orders?
- Are weekly audit logs signed by the Maintenance Director and reviewed at monthly QAPI meetings?
3-Question Hallway Spot-Quiz
Review with nurses & CNAs during your 5-minute shift huddle:
- If you spot an equipment or corridor safety issue related to K-761, how do you report an urgent maintenance order?
- Where are weekly Life Safety inspection logs kept when state surveyors arrive?
- What safety check happens on your unit before ending your shift?
Approved State Plan Examples for K0761
Yorkview Nursing and Rehabilitation (PA)
Spot-checks: monthly × 4 weeks
✓ Passed Re-Inspection
Development and/or execution of this plan of correction does not constitute admission or agreement by this provider of the truth in the statement of deficiency. This plan of correction is…
View Full Plan Text (06/09/2026)
K0761 Correction Date: 07/24/2026
Development and/or execution of this plan of correction does not constitute admission or agreement by this provider of the truth in the statement of deficiency. This plan of correction is prepared and/or executed by provision of Federal or State Law.
1. The Maintenance Department conducted an annual inspection of all rated/labeled doors in the facility.
2. Completion date 7/13/26.
3. The Maintenance Department has been educated to visually inspect all facility fire doors and to complete documentation.
4. NHA/Designee will audit life safety book semi-annually to confirm the annual fire door inspection has been filed, and any deficiencies have been addressed, and scheduled date of the next inspection. Findings will be reviewed at the monthly Quality Assurance and Performance Improvement Committee to address further action planning or the need for further review.
5. Date of compliance: 7/24/26
Arbor Grove Village (IN)
Spot-checks: daily × 4 weeks
✓ Passed Re-Inspection
1. What corrective action will be accomplished for those residents found to have been affected by the deficient practice; Some residents could potentially 2. How other residents having the…
View Full Plan Text (05/27/2026)
K0761
Completion Date: 06/25/2026
1. What corrective action will be accomplished for those residents found to have been affected by the deficient practice; Some residents could potentially
2. How other residents having the potential to be affected by the same deficient practice will be identified and what corrective action will be taken; Some residents could potentially be affected by this alleged deficient practice. Maintenance director in-serviced on 5/28/26 on conducting annual fire door testing to 400 hall door, 200 hall door and Oxygen Transfilling room door and include on report.
3. What measures will be put into place and what systemic changes will be made to ensure that the deficient practice does not recur; Maintenance director or designee will use Life safety code/QAPI tool to audit annual fire door testing to 400 hall door, 200 hall door and Oxygen Transfilling room door and include on report. Maintenance Director or designee will complete ongoing monitoring via QAPI program with meetings held bi-monthly and is overseen by the Executive Director. The Maintenance Director will audit daily (5x week) for 4 weeks, monthly x 6 months, using Life Safety/QAPI Audit tool and thereafter QAPI committee will determine need for further review. The results of these audits will be reviewed by the QAPI committee, if threshold of 100% is not achieved an action plan will be revised/completed.